Ohio County Schools Bond Project Updates

Last updated July 12, 2022

In partnership with Ohio County Schools, McKinley Architecture and Engineering has launched a Bond Updates page. The following is a summary schedule for projects taking place in 2019, along with others scheduled to begin in 2020 and 2021. It is important to keep in mind that the design and planning for each of the bond projects begins before actual construction. The design phase includes programming, schematic design, design development, construction documents, and state reviews for approval. We look forward to providing updates to this page on the status of OCS bond projects.

To learn more about McKinley Architecture and Engineering's capabilities and accomplishments, please click here.

Click here to send Ohio County Schools your feedback.


Executive Summary

In 2018 Ohio County residents passed a bond for $42,000,000 to improve and enhance buildings across Ohio County. With an additional $27,000,000 from the SBA, $6,300,000 in energy savings contracts and $14,615,490 in other funding sources, Ohio County Schools has made (plans to make) significant improvements across all 13 schools. Please note there was another approximately $15 million worth of work performed by CMTA Energy. These numbers were not calculated into the information below. Some of their work is still to come with the projects that are ongoing now.

Overall Budget $89,915,490
2018 Bond Budget $75,300,000
Additional Funding Sources $14,615,490
Total Projected Project Costs (as of 07/12/22) $89,532,784
Total Over/Under Under Budget by $382,706
Budget
Overall Budget $89,915,490
2018 Bond Budget - $75,300,000
Additional Funding Sources - $14,615,490
Total Projected Project Costs (as of 07/12/22)
$89,532,784
Total Over/Under
Under Budget by $382,706

*Note: The financial picture changes as we progress through design, bidding and construction.


Current Projects

Project Design Procurement / Bidding Construction Bond Budget Variance
Steenrod Elementary School Roof Replacement
Elm Grove Elementary School Roof Replacement
Triadelphia Middle School Bleacher Replacement
Wheeling Middle School Bleacher Replacement
Wheeling Park High School Bleacher Replacement
Completed
Completed
Completed
On Budget
Triadelphia Middle School Addition and Renovation
Triadelphia Middle School Addition and Renovation
Add safety/security lighting; addition to original 1917 school to replace existing 1922 annex and related improvements; new site stair between adjacent elementary and school; classroom renovations to repurpose spaces; flooring, ceiling, and roof replacements; HVAC systems upgrade; and bleacher replacement
Completed
Completed
Completed
$162,724
Renovations to Triadelphia Middle Schools were funded with SBA funds for the first round from the SBA. $9M came from the SBA and the remaining amount from OCS. Enhancements made to the building include but not limited to additional HVAC unit replacements at TMS in order to provide better air quality throughout the building. A total Sprinkler system for the original TMS building was added to the project. Parking spots were added between Steenrod and TMS. Sanitary and Storm Lines were also separated.
Bridge Street Middle School Renovation
Bridge Street Middle School Renovation
Safety and security renovations to upgrade visitor access and parking; reconfigure circulation to relocate entry to original front entry; repairs to address water infiltration, add exterior safety/security lighting, corrections and replacements to interior doors & hardware; renovations to enhance music curriculum; ceiling, flooring, window, and roof replacements; HVAC systems upgrade; and new sprinkler system
Completed
Completed
Completed
On Budget
On budget
Ritchie Elementary School Renovation
Ritchie Elementary School Renovation
Upgrade site fencing, and parking and playground areas; additional exterior safety/security enhancements; ceiling, flooring, and window replacements; HVAC systems upgrade in 1976 addition; fire alarm upgrades; and repairs to drinking fountains and swimming pool
Completed
Completed
Completed
$423,811
Renovations Ritchie Elementary Schools were 100% funded by OCS bond issue. Enhancements made to the building include but not limited to the roof replacement at Ritchie, access control upgrades and makerspace renovations.
Madison Elementary School Renovation
Madison Elementary School Renovation
Improve drop-off area; upgrade bus loading zone and site fencing, and parking and playground areas; additional exterior safety/security enhancements and lighting; replacements of exterior door and windows; restoration of building exterior; security/accessibility entrance renovation; code compliance renovations to kitchen; interior accessibility improvements; classroom renovations; flooring, window, and roof replacements; HVAC systems upgrade; and fire alarm and sprinkler systems upgrades
Completed
Completed
Completed
($101,832)
Under budget
Steenrod Elementary School Addition and Renovation
Steenrod Elementary School Addition and Renovation
Improve drop-off area; upgrade bus loading zone and parking areas; kitchen/cafeteria addition; additional exterior safety/security enhancements and lighting; security entrance renovation; repair interior doors & hardware; classroom renovations; flooring, window, and roof replacements; and HVAC and electrical systems upgrade
Completed
Completed
Completed
$945,803
Renovations to West Liberty and Steenrod Elementary Schools were 100% funded by OCS bond issue. Enhancements made to the building include but not limited to additional HVAC Units were replaced, new concrete entrance and flooring was replaced throughout the building.
West Liberty Elementary School Renovation
West Liberty Elementary School Renovation
Add safety/security lighting; classroom renovations; security entrance renovation; repairs to building exterior; improvements to interior door hardware; flooring, ceiling, and window replacements; concrete slab corrections; HVAC systems upgrade; and bleacher replacement
Completed
Completed
Completed
($463,740)
Renovations to West Liberty and Steenrod Elementary Schools were 100% funded by OCS bond issue. Enhancements made to the building include but not limited to additional HVAC Units were replaced, new concrete entrance and flooring was replaced throughout the building.
WPHS Athletic Field/Track
Completed
Completed
In Progress
In Progress

Completion Anticipated
Summer 2022

$2,079,442
This was 100% funded by OCS Bond Issue. Enhancements made to the project include but not limited to at the athletic field new lights, wider field, additional concrete work and storage and restroom buildings. At the track a new concession / timer / referee building and then renovations to upgrade public restrooms in the locker room facility among other items at the track.
Wheeling Park High School Addition and Renovation
Wheeling Park High School Addition and Renovation
Add safety/security lighting; slop repairs at track; add artificial turf to existing field; restroom addition to track complex; upgrade softball field; security entrance addition; administration area renovations; performing arts areas renovations and addition; media center renovations; science lab renovations; improvements to food service areas; upgrades to career and technical education (CTE) equipment; locker room renovations; selective slab corrections; flooring, roofing, window, exterior overhead door, ceiling and roof replacements; swimming pool equipment replacements; security and electrical systems upgrades; repair interior doors; HVAC systems upgrade; and bleacher replacement
Completed
Completed
In Progress
In Progress

Completion Anticipated
Summer 2022

$2,667,354
This building was 100% funded by OCS bond issue. Enhancements made to the building include but not limited to a full renovation of the locker rooms, better acoustics throughout the music department, full renovation of the Science Department, Media Center full renovation and additional concrete work at the main entrance.
Bethlehem Elementary School Renovation
Bethlehem Elementary School Renovation
Safety and security renovations to upgrade site fencing, reconfigure entry to add security vestibule, replace interior doors and hardware; ceiling, flooring, window, and roof replacements; HVAC systems upgrade; and new sprinkler system
Completed
Completed
In Progress
In Progress
$117,978
This project is funded by SBA and OCS bond issue. Additional ESSERF funds will allow for OCS to enhance the scope of this project. Bethlehem project is completing all new exterior window upgrades, new fire alarm system, replacing the oldest section of the roof, new soffit for the entrance canopy with upgraded lighting, replaced the fencing and created additional parking spots, painting, flooring, and mechanical work.
Warwood School Renovation
Warwood School Renovation
Upgrade parking areas; add exterior safety/security lighting and other enhancements; security entrance renovation; flooring, ceiling, window, and roof replacements; improvements to interior doors & hardware, water damage and drinking fountains; electrical systems upgrade; new sprinkler system in elementary school portion of building; and HVAC systems upgrade
Completed
Completed
In Progress
In Progress
$2,660,056
This project is funded by SBA, OCS Bond Issue and ESSERF. Warwood project was able to take advantage of the ESSERF funding that came through for Ohio County Schools. This amount is being utilized to replace the existing HVAC System and exterior windows at Warwood. The project was able to keep a high-level HVAC system in the project and complete the entire building HVAC System Replacement.
Woodsdale Elementary School Addition and Renovation
Woodsdale Elementary School Addition and Renovation
Kitchen/cafeteria renovation; upgrade drop-off area, bus loading zone and parking areas; security entrance renovation; improvements to interior doors and hardware; classroom renovations; selective repairs to building exterior; flooring, exterior door, and window replacements; and HVAC and electrical systems upgrades;
Completed
Completed
In Progress
In Progress
$1,151,786
This project is funded by SBA, OCS Bond Issue and ESSERF. Woodsdale project is able to utilize ESSERF funding for the HVAC system upgrade at Woodsdale. The remaining portion of the building will be funded through the SBA/OCS funds. This includes a complete renovation of the academic wing of the building, new exterior windows, hardware, fire alarm system, cafeteria addition and an addition for the main entrance to create a “man trap”.
Wheeling Middle School Addition and Renovation
Wheeling Middle School Addition and Renovation
Construct addition connected to original 1977 school for security entrance, circulation (stair & elevator) to main floor level and administration area; upgrades to parking areas; exterior safety/security enhancements and lighting; classroom renovations; flooring, window, exterior doors, ceiling and roof replacements; HVAC and plumbing systems upgrade; and bleacher replacement
Completed
Completed
In Progress
In Progress

Completion Anticipated
2022

On Budget
This project is being funded by the SBA and OCS Bond Issue. Additional ESSERF funds will allow for OCS to enhance the scope of this project. Wheeling Middle School is to be bid sometime in December or the first of the year. This project will include new “man trap”, new elevator, HVAC system upgrades, makerspace, science rooms and some new finishes throughout the building.
Middle Creek Elementary School Addition and Renovation
Middle Creek Elementary School Addition and Renovation
Improve drop-off area; upgrade bus loading zone and site fencing, and parking and playground areas; additional exterior safety/security enhancements; renovation of security entrance, cafeteria and gymnasium; addition to replace spaces used for cafeteria and security entrance renovations; ceiling, flooring, window, and roof replacements; HVAC systems upgrade; and fire alarm and sprinkler systems upgrades
In Progress
In Progress

Construction Begins (Anticipated)
Spring 2023

$1,429,666
Renovations to Elm Grove and Middle Creek Elementary Schools are being funded by the SBA and OCS Bond Issue. Additional ESSERF funds will allow for OCS to enhance the scope of these projects. Elm Grove / Middle Creek scope is upgrading the finishes throughout the facilities, site improvements among other items within the facility. The insertion of additional funds will allow for the buildings to be re-evaluated and confirm the complete scope. This will be done once we have bid out everything but Elm Grove and Middle Creek.
Elm Grove Elementary School Addition and Renovation
Elm Grove Elementary School Addition and Renovation
Improve drop-off area; upgrade bus loading zone and site fencing, and parking and playground areas; additional exterior safety/security enhancements and lighting; renovation of security entrance, cafeteria and gymnasium; addition to replace spaces used for cafeteria and security entrance renovations; ceiling, flooring, window, and roof replacements; HVAC systems upgrade; and fire alarm and sprinkler systems upgrades
In Progress
In Progress

Construction Begins (Anticipated)
Spring 2023

$1,429,666
Renovations to Elm Grove and Middle Creek Elementary Schools are being funded by the SBA and OCS Bond Issue. Additional ESSERF funds will allow for OCS to enhance the scope of these projects. Elm Grove / Middle Creek scope is upgrading the finishes throughout the facilities, site improvements among other items within the facility. The insertion of additional funds will allow for the buildings to be re-evaluated and confirm the complete scope. This will be done once we have bid out everything but Elm Grove and Middle Creek.
Steenrod Elementary School Roof Replacement
View Media
Status
Completed
Bond Budget Variance
On Budget
Elm Grove Elementary School Roof Replacement
View Media
Status
Completed
Bond Budget Variance
On Budget
Triadelphia Middle School Bleacher Replacement
View Media
Status
Completed
Bond Budget Variance
On Budget
Wheeling Middle School Bleacher Replacement
View Media
Status
Completed
Bond Budget Variance
On Budget
Wheeling Park High School Bleacher Replacement
View Media
Status
Completed
Bond Budget Variance
On Budget
Triadelphia Middle School Addition and Renovation
Add safety/security lighting; addition to original 1917 school to replace existing 1922 annex and related improvements; new site stair between adjacent elementary and school; classroom renovations to repurpose spaces; flooring, ceiling, and roof replacements; HVAC systems upgrade; and bleacher replacement
View Media
Status
Completed
Bond Budget Variance
$162,724
Renovations to Triadelphia Middle Schools were funded with SBA funds for the first round from the SBA. $9M came from the SBA and the remaining amount from OCS. Enhancements made to the building include but not limited to additional HVAC unit replacements at TMS in order to provide better air quality throughout the building. A total Sprinkler system for the original TMS building was added to the project. Parking spots were added between Steenrod and TMS. Sanitary and Storm Lines were also separated.
Bridge Street Middle School Renovation
Safety and security renovations to upgrade visitor access and parking; reconfigure circulation to relocate entry to original front entry; repairs to address water infiltration, add exterior safety/security lighting, corrections and replacements to interior doors & hardware; renovations to enhance music curriculum; ceiling, flooring, window, and roof replacements; HVAC systems upgrade; and new sprinkler system
View Media
Status
Completed
Bond Budget Variance
On Budget
On budget
Ritchie Elementary School Renovation
Upgrade site fencing, and parking and playground areas; additional exterior safety/security enhancements; ceiling, flooring, and window replacements; HVAC systems upgrade in 1976 addition; fire alarm upgrades; and repairs to drinking fountains and swimming pool
View Media
Status
Completed
Bond Budget Variance
$423,811
Renovations Ritchie Elementary Schools were 100% funded by OCS bond issue. Enhancements made to the building include but not limited to the roof replacement at Ritchie, access control upgrades and makerspace renovations.
Madison Elementary School Renovation
Improve drop-off area; upgrade bus loading zone and site fencing, and parking and playground areas; additional exterior safety/security enhancements and lighting; replacements of exterior door and windows; restoration of building exterior; security/accessibility entrance renovation; code compliance renovations to kitchen; interior accessibility improvements; classroom renovations; flooring, window, and roof replacements; HVAC systems upgrade; and fire alarm and sprinkler systems upgrades
View Media
Status
Completed
Bond Budget Variance
($101,832)
Under budget
Steenrod Elementary School Addition and Renovation
Improve drop-off area; upgrade bus loading zone and parking areas; kitchen/cafeteria addition; additional exterior safety/security enhancements and lighting; security entrance renovation; repair interior doors & hardware; classroom renovations; flooring, window, and roof replacements; and HVAC and electrical systems upgrade
View Media
Status
Completed
Bond Budget Variance
$945,803
Renovations to West Liberty and Steenrod Elementary Schools were 100% funded by OCS bond issue. Enhancements made to the building include but not limited to additional HVAC Units were replaced, new concrete entrance and flooring was replaced throughout the building.
West Liberty Elementary School Renovation
Add safety/security lighting; classroom renovations; security entrance renovation; repairs to building exterior; improvements to interior door hardware; flooring, ceiling, and window replacements; concrete slab corrections; HVAC systems upgrade; and bleacher replacement
View Media
Status
Completed
Bond Budget Variance
($463,740)
Renovations to West Liberty and Steenrod Elementary Schools were 100% funded by OCS bond issue. Enhancements made to the building include but not limited to additional HVAC Units were replaced, new concrete entrance and flooring was replaced throughout the building.
WPHS Athletic Field/Track
Status
Construction In Progress

Completion (Anticipated)
Summer 2022

Bond Budget Variance
$2,079,442
This was 100% funded by OCS Bond Issue. Enhancements made to the project include but not limited to at the athletic field new lights, wider field, additional concrete work and storage and restroom buildings. At the track a new concession / timer / referee building and then renovations to upgrade public restrooms in the locker room facility among other items at the track.
Wheeling Park High School Addition and Renovation
Add safety/security lighting; slop repairs at track; add artificial turf to existing field; restroom addition to track complex; upgrade softball field; security entrance addition; administration area renovations; performing arts areas renovations and addition; media center renovations; science lab renovations; improvements to food service areas; upgrades to career and technical education (CTE) equipment; locker room renovations; selective slab corrections; flooring, roofing, window, exterior overhead door, ceiling and roof replacements; swimming pool equipment replacements; security and electrical systems upgrades; repair interior doors; HVAC systems upgrade; and bleacher replacement
View Media
Status
Construction In Progress

Completion (Anticipated)
Summer 2022

Bond Budget Variance
$2,667,354
This building was 100% funded by OCS bond issue. Enhancements made to the building include but not limited to a full renovation of the locker rooms, better acoustics throughout the music department, full renovation of the Science Department, Media Center full renovation and additional concrete work at the main entrance.
Bethlehem Elementary School Renovation
Safety and security renovations to upgrade site fencing, reconfigure entry to add security vestibule, replace interior doors and hardware; ceiling, flooring, window, and roof replacements; HVAC systems upgrade; and new sprinkler system
Status
Construction In Progress
Bond Budget Variance
$117,978
This project is funded by SBA and OCS bond issue. Additional ESSERF funds will allow for OCS to enhance the scope of this project. Bethlehem project is completing all new exterior window upgrades, new fire alarm system, replacing the oldest section of the roof, new soffit for the entrance canopy with upgraded lighting, replaced the fencing and created additional parking spots, painting, flooring, and mechanical work.
Warwood School Renovation
Upgrade parking areas; add exterior safety/security lighting and other enhancements; security entrance renovation; flooring, ceiling, window, and roof replacements; improvements to interior doors & hardware, water damage and drinking fountains; electrical systems upgrade; new sprinkler system in elementary school portion of building; and HVAC systems upgrade
Status
Construction In Progress
Bond Budget Variance
$2,660,056
This project is funded by SBA, OCS Bond Issue and ESSERF. Warwood project was able to take advantage of the ESSERF funding that came through for Ohio County Schools. This amount is being utilized to replace the existing HVAC System and exterior windows at Warwood. The project was able to keep a high-level HVAC system in the project and complete the entire building HVAC System Replacement.
Woodsdale Elementary School Addition and Renovation
Kitchen/cafeteria renovation; upgrade drop-off area, bus loading zone and parking areas; security entrance renovation; improvements to interior doors and hardware; classroom renovations; selective repairs to building exterior; flooring, exterior door, and window replacements; and HVAC and electrical systems upgrades;
Status
Construction In Progress
Bond Budget Variance
$1,151,786
This project is funded by SBA, OCS Bond Issue and ESSERF. Woodsdale project is able to utilize ESSERF funding for the HVAC system upgrade at Woodsdale. The remaining portion of the building will be funded through the SBA/OCS funds. This includes a complete renovation of the academic wing of the building, new exterior windows, hardware, fire alarm system, cafeteria addition and an addition for the main entrance to create a “man trap”.
Wheeling Middle School Addition and Renovation
Construct addition connected to original 1977 school for security entrance, circulation (stair & elevator) to main floor level and administration area; upgrades to parking areas; exterior safety/security enhancements and lighting; classroom renovations; flooring, window, exterior doors, ceiling and roof replacements; HVAC and plumbing systems upgrade; and bleacher replacement
Status
Construction In Progress

Completion (Anticipated)
2022

Bond Budget Variance
On Budget
This project is being funded by the SBA and OCS Bond Issue. Additional ESSERF funds will allow for OCS to enhance the scope of this project. Wheeling Middle School is to be bid sometime in December or the first of the year. This project will include new “man trap”, new elevator, HVAC system upgrades, makerspace, science rooms and some new finishes throughout the building.
Middle Creek Elementary School Addition and Renovation
Improve drop-off area; upgrade bus loading zone and site fencing, and parking and playground areas; additional exterior safety/security enhancements; renovation of security entrance, cafeteria and gymnasium; addition to replace spaces used for cafeteria and security entrance renovations; ceiling, flooring, window, and roof replacements; HVAC systems upgrade; and fire alarm and sprinkler systems upgrades
Status
Design In Progress

Construction Begins (Anticipated)
Spring 2023

Bond Budget Variance
$1,429,666
Renovations to Elm Grove and Middle Creek Elementary Schools are being funded by the SBA and OCS Bond Issue. Additional ESSERF funds will allow for OCS to enhance the scope of these projects. Elm Grove / Middle Creek scope is upgrading the finishes throughout the facilities, site improvements among other items within the facility. The insertion of additional funds will allow for the buildings to be re-evaluated and confirm the complete scope. This will be done once we have bid out everything but Elm Grove and Middle Creek.
Elm Grove Elementary School Addition and Renovation
Improve drop-off area; upgrade bus loading zone and site fencing, and parking and playground areas; additional exterior safety/security enhancements and lighting; renovation of security entrance, cafeteria and gymnasium; addition to replace spaces used for cafeteria and security entrance renovations; ceiling, flooring, window, and roof replacements; HVAC systems upgrade; and fire alarm and sprinkler systems upgrades
Status
Design In Progress

Construction Begins (Anticipated)
Spring 2023

Bond Budget Variance
$1,429,666
Renovations to Elm Grove and Middle Creek Elementary Schools are being funded by the SBA and OCS Bond Issue. Additional ESSERF funds will allow for OCS to enhance the scope of these projects. Elm Grove / Middle Creek scope is upgrading the finishes throughout the facilities, site improvements among other items within the facility. The insertion of additional funds will allow for the buildings to be re-evaluated and confirm the complete scope. This will be done once we have bid out everything but Elm Grove and Middle Creek.